| Rhode Peaking Capacity Project |
 |
| Client: |
ESB Power Generation |
| Engineer: |
ESB International |
| Architect: |
N/A |
| Value: |
Private Client |
| Period: |
April 2004 - August 2004 |
Description:
Lead in time on the project was one weekend with 70% of civil works completed
within the first two months. All target dates as set down in the contract were
met or exceeded.
Works included:
-
Excavation & Disposal of 25,000m3 of peaty material
-
Two new reinforced concrete bases with excess of 600m3 of concrete in each
-
Steel storage tank foundations
-
HDPE-lined bunded compound for oil tanks
-
Reinforced concrete slabs and bunds for transformers
-
Steel-framed buildings
-
All associated site works
|
|
|