Description:
This is a design and build project for the upgrading of the recently
constructed Balbriggan & Skerries wastewater treatment plant (phase 1) from
its original design capacity of 30,000 PE to 70,000 PE.
The project included the construction of the following:
-
Construction of a large in-situ concrete SBR tank
-
Construction of a UV treatment unit
-
Interconnecting pipework
-
Ducting works
-
Road construction
-
Landscaping works
-
Sewer diversion works
|