Dunleer Overbridge 99A
Client: Iarnrod Eireann
Engineer: Roughan & O'Donovan
Architect: N/A
Value: c. €2M
Period: July 2002 - May 2003

Description:

This project was technically challenging to the project team, consisting of difficult bearing installation underneath sloping beams in conjunction with working within the constraints of the railway authority. Works included the interface to the public road at the north side and the associated access roads, fencing, landscaping and decommissioning of the existing redundant level crossing.