This project which commenced in September 2001 involved the construction of a
seven span composite precast / in-situ concrete bridge crossing a railway and
a canal with associated roadworks, earthworks, embankments and realigning
walls.
The roadwork's comprised of approximately 800 linear meters of distributor
road, consisting of flexible carriageway pavement, earthworks, surface water
drainage, footpaths and cycle paths, traffic signs and road markings, street
lighting.
Earthworks comprised of excavations in domestic waste fill and limestone rock
for construction of the structural foundations. Embankments, constructed in
suitable fill material were required at the approaches to the structure.
|