Description:
The projects involves the diversion of Utility Services within a main services
trench routed to co-ordinate with the future Terminal 2 arrivals roadway. The
diversion of the following Utility Services:
-
ESB 38kV and 10kV cabling and ducting
-
Bord Gais gas main pipework
-
Eircom fibre and copper cabling
-
All DAA 10kV and 400V cabling
The project also involves the site clearance of below ground services
and above ground associated street furniture and shrubbery within the
footprint of Terminal 2 and associated road ways construction area.
The demolition of several buildings including the controlled demolition
of Corbalis House.
Tanks moved/replaced.
|